The nuclear tender is in the final stage, KHNP submitted a bid a day earlier than EDF

The nuclear tender is in the final stage, KHNP submitted a bid a day earlier than EDF
The nuclear tender is in the final stage, KHNP submitted a bid a day earlier than EDF
--

The original deadline for the submission of considered offers for the construction of nuclear units in the Czech Republic was set for April 15. The bag moved to the EDF warehouse and to the end of the month. According to EZ, the French company doubled its share at the time with internal approval processes.

France makes no secret of its ambitions to become the leader of the European nuclear renaissance. This is also why EDF itself would like to succeed in the Czech nuclear tender. As part of the EPR1200 EPR1200 reactor project, Piem emphasizes that it is a technology that is the only one that is 100% Made in Europe.

esk industry should be so involved

According to its representatives, EDF wants to involve the same percentage of domestic companies in the construction of new nuclear power plants as it did in the case of the Hinkley Point nuclear power plant in Great Britain.

I confirm that EDF owns a 64 percent share of Czech companies, said Roman Zdebor, the representative of the company in Czech. As he added, every crown invested in the nuclear project should mean an increase of 3.27 K for the Czech economy.

According to EDF’s plans, Czech companies could then take part in other projects in Europe that EDF wants to implement in the future. EDF’s offer puts the country in the center of the nuclear renaissance, it was announced at the company’s press conference.

KHNP thus committed to it that it intended to involve Czech companies in the project, namely Piblin, on the same level as EDF. In the course of the campaigns, the South Korean company highlighted the fact that in the past fifty years it had not managed to build nuclear blocks even for a single day. First of all, thanks to this experience, according to representatives, the company is ready to meet any requirements from the client. The South Koreans are raising the price of the new reactors in Esk until their company KHNP builds them for a pre-agreed amount. In addition, using a turbocharger made of Doosan Koda Power.

We had it all ready and wanted to minimize the risk. That’s why we decided to extend the offer by two days. In addition to the fifth block in Dukovany, this included consideration of options for those dal blocks, which are six blocks in Dukovany and dal two in Temeln. We wanted to be prepared for all eventualities, whatever could happen, explained his procedure in front of the EZ meeting on Monday morning, the executive editor of KHNP u Ho-wang, who personally delivered the dark blue box with its contents to the editor-in-chief and chairman of the EZ board, Daniel Bene.

In the case of the KHNP, it was a gesture, but from their point of view, nothing is due. It was supposed to underline the fact that the Koreans are prepared for all variants and would proceed in the same way even if they were given the opportunity to build new nuclear blocks in Russia. In fact, bids for the tender are sent electronically via a secure route, as confirmed by EZ spokesman Ladislav K.

For the Czech nuclear power plant, the KHNP reactor APR1000 with a capacity of 1050 MWe. He received the EUR certification last year. The reactor was first designed by the KHNP company for export to European countries and was adapted to meet European conditions and meet the requirements based on the latest standards in terms of safety, economic criteria and structural capability, both from the point of view of the International Atomic Energy Agency (IAEA), as well as the West European Nuclear Regulatory Association (WENRA).

if we are fully committed to it. We did everything to be a valuable partner from the initial stages of the tender. Even if the Czech side came up with new requirements and conditions, we are ready to respond flexibly so that this project will go through as soon as possible, the executive editor of KHNP told iDNES.cz.

EZ before the government will apply in April

At the end of January this year, the government invited EDF and KHNP to submit considered offers for the reactor. After analyzing the first project, she decided to build one reactor in Dukovany, which included options for additional units. According to Prime Minister Petr Fiala (ODS), the unconsidered bids of the applicants for the construction of the reactor turned out to be 25 percent more suitable than the construction of only one block. The government did not specify the specific amount.

On the other hand, the North American company Westinghouse, which, according to the Cabinet, did not meet the conditions of the original tender, dropped out of the original trio of candidates for the nuclear tender. According to some people, however, the American concern Westinghouse did not approach it with full commitment. The reason was the disappointment of the two women who were hired to complete the construction of the Temelna block, which was demolished in April 2014.

At that time, the Americans invested a lot of money and effort in the preparations, their disappointment was great. In addition, in the current tender they did not have one center and a representative, it would be possible to communicate with them, which is appreciated by the EZ and the Czech government, the source said.

Vtzi will be decided by luck

EZ, which is in charge of the current tender for the construction of new nuclear units in the Czech Republic, is therefore analyzing the bids submitted by EDF and KHNP and should submit them to the government for assessment in April. The Cabinet will then decide who will be the recipient and exactly how many blocks should actually be built in the Czech Republic.

It is assumed that the contracts will be finalized during this year and prepared for signing by the 31st of March of the following year. After their final signature, according to the EZ, a thorough revision of the documentation projects will follow, so that the deadline for trial operation of the new unit in 2036 can be reached.

According to two reports by the government and the EZ, one new reactor should cost about K 160 billion in 2020 prices. Representatives of EDF, KHNP, and the Czech party refuse to comment in any way on the prices in the offers. Some economists estimated in January that the construction of the reactor could cost up to two trillion crowns.

Given that this is the largest project in the history of the Czech Republic, it is not only the case of one company. We are ready to support him, said Ambassador of the Republic of Korea Youngki Hong on Monday before the EC meeting.

According to him, the Korean government is considering various options for co-financing this large project, or how to financially support it.

The ambassador confirmed that the Korean government provided certain forms of support for the construction of the Barka nuclear power plant in the United Arab Emirates, where the KHNP company built those nuclear blocks.

That possibility is how many. Moreover, from our point of view, it is also an opportunity for further cooperation and implementation of projects, such as the construction of high-speed railways or small modular reactors, e.g.

Czechia currently has six nuclear units in two power plants. Two units, each with a capacity of 1,000 megawatts (MW), are located in southern Temeln. those two blocks with a capacity of 510 MW are located in Dukovany in Tebsko. In addition to the new classic reactors, EZ is preparing the construction of small modular reactors. The first of them should be created in Temeln.

Support for the development of nuclear energy in the Czech Republic is above 70 percent, which is a uniquely high level of support in Europe. Find it out from a long-term survey by the IBRS agency.